Seven published steps take a seamless pipe from a hollow to a tested length: forming, heat treatment, pickling, cutting, inspection.

Format
Explainer
Published
Duration
2 min 17 sec
Language
English
Full explainer series: Junda Explainers

About this video

This explainer follows the route Junda publishes on the production-environment page. The 6–630 mm outside diameter and 0.2–80 mm wall are a manufacturing range, not a per-grade stock list; certificate type, dimensions and documents are confirmed in the quotation.

Chapters

Each chapter opens the video at that point on YouTube.

  1. 0:00

    Seamless pipe manufacturing process: from hollow to cold forming

    The seamless pipe manufacturing process starts with a hollow, not a sheet. Seven published steps take that hollow to a tested length. The first is the raw material: a hollow with a bore already through it, so no weld has to be made later. The hollow starts heavy: a thick wall around a bore that is already open. The second step is cold forming: a pilger stand rolls the wall down, then a draw die pulls it thinner. Seven cold rolling mills and seven cold drawing machines do that work, as published. The wall follows the pass: it comes down while the outside and the bore are held. The published range is 6 to 630 millimetres outside diameter, and 0.2 to 80 millimetres of wall. That is what the route can make, not what is on the shelf.

  2. 0:52

    What solution heat treatment does in a seamless tube route

    The third step is solution heat treatment: the tube runs through a furnace. Two published lines run it, and the condition that comes out is what the certificate will name.

  3. 1:04

    Pickling, straightening and cutting a seamless tube

    A furnace leaves an oxide layer on the surface. The fourth step is pickling: an acid tank takes that layer off, and six published systems do the work. The fifth step is straightening: skew rolls take the bow out of the length. The sixth step is cutting: a saw cuts the length you ordered. Straight lengths leave the line as they are. A U-bend or a rectangular transfer tube is formed from a straight length afterwards. The route is the same; the last operation is not.

  4. 1:34

    How a seamless tube is inspected and certified

    The seventh step is inspection: a probe ring scans the length, and a pressure test follows. The published inspection table covers seven test groups. None of those steps starts a new identity: the heat number is written at the raw material. So the certificate can tie the delivered length back to the heat that was tested.

  5. 1:55

    How to write a seamless pipe order: grade, size, condition

    The route is fixed, so what you choose is what the route has to prove. Grade, and its UNS designation. Outside diameter, wall, and length. Condition, and the certificate type that proves it. Junda confirms the size, the documents and the scope in the quotation. Send Junda the grade, the size and the documents your order needs.

Specify the pipe or tube for your project

Send the grade, standard, OD × wall × length, wall basis, quantity, inspection and documents with your enquiry.