Stainless steel tube sizes: what NPS, OD and wall fix

NPS 4 is 114.3 mm outside, not four inches: schedule 40S is 6.02 mm at NPS 4 and 10.31 mm at NPS 12, and the wall basis decides what arrives.

Format
Explainer
Published
Duration
3 min 14 sec
Language
English
Full explainer series: Junda Explainers

About this video

This explainer is educational. The dimensions and masses come from the published ASME B36.19 chart and Junda's published weight formula; a size is only an order when the standard, grade, wall basis, length, tests and documents are written with it. Confirm them on the quotation for each order.

Chapters

Each chapter opens the video at that point on YouTube.

  1. 0:00

    Stainless steel tube sizes: what NPS, OD and wall fix

    Stainless steel tube sizes are written in two numbers. A pipe puts a name in front of them, and the name is where a size gets lost. NPS four is 114.3 millimetres of outside diameter. Four inches is 101.6.

  2. 0:16

    Why NPS 4 is 114.3 mm and not four inches

    NPS is a trade size. It is not a diameter. NPS four is published at 114.3 millimetres outside diameter, in every schedule. Every schedule at NPS four shares that one outside diameter. Measured with a tape, four inches is 101.6 millimetres. One number is a name. The other is a dimension, and the mill works to the dimension.

  3. 0:41

    Stainless steel tube sizes: outside diameter, wall and bore

    The first number is outside diameter. The second is wall. At NPS four, schedule 40S gives a wall of 6.02 millimetres. Take that off twice and the bore is 102.26. The bore is never ordered. It is what the two numbers leave behind. Keep the outside diameter and change the schedule, and the wall moves. Schedule 80S is 8.56 millimetres on the same pipe. The bore closes to 97.18. Same name, same outside diameter, a heavier pipe. The schedule is a table, not a number. 40S is 3.38 millimetres at NPS one, and 10.31 at NPS twelve. At four it is 6.02. At eight it is 8.18. So the words schedule 40S never give you the wall on their own.

  4. 1:31

    How the wall changes the weight per metre

    Those same two numbers set the weight. Wall, times outside diameter minus wall, times density, pi over one thousand. NPS four in 40S is 16.38 kilograms a metre in TP316L. The same pipe in 80S is 22.75. At NPS eight in 40S, 43.36.

  5. 1:54

    How the mill makes the wall: cold rolling, drawing and heat treatment

    The wall is not a promise on paper. It is drawn and rolled into the pipe. Junda publishes 7 cold rolling mills, 7 cold drawing machines and 2 heat treatment lines. Then straightening takes the curve out of it. Cutting sets the length. Then inspection checks the wall, piece by piece. A tube is written without the trade name. Outside diameter, wall and length, with the tolerance agreed in the order. A U-bend adds bend radius, centre distance and leg length. A rectangular tube adds width and height, and a corner radius. Same question, and more numbers to fix before the mill can quote.

  6. 2:32

    How to write a size on an enquiry: wall basis, length and tests

    One word decides what arrives: the wall basis. On average wall, the nominal wall is an average of the wall around the pipe. On minimum wall, the nominal number is the thinnest point the order accepts. The published checklist calls a missing basis one of the most frequent causes of disputes. Written in one line, the size stops being an argument. Grade and UNS. Standard and edition. NPS and its millimetres. Schedule or wall, with the basis. Then length, tests and documents. That is a line a mill can quote without asking three questions. Send the grade, the size, the wall basis and the tests, and we confirm the pipe against them.

Specify the pipe or tube for your project

Send the grade, standard, OD × wall × length, wall basis, quantity, inspection and documents with your enquiry.